NSW Court IT: AU$18m too costly, two years too late

NSW courts may have had a good year in case management terms, but have been let down by the delay and budget overrun in the implementation of its Web-based JusticeLink administration system.

The JusticeLink system is expected to be fully implemented across all NSW jurisdictions by July 2008, according to a report released yesterday by the state Auditor General's Department.

Work on the system commenced initially in 2001, with a view to completion by 2006. However, delays occurred early in the project after tests indicated that the software could not meet the needs of each court across the respective jurisdictions.

The original cost estimate of the system was AU$30.3 million, but yesterday's report said the total capital cost for the project is now estimated at AU$48.2 million, with AU$8.1 million in recurrent expenditure.

A spokesperson for the Attorney-General's Department said that the AU$30.3 million figure "was estimated prior to the department entering into the initial contract for the project and didn't represent the full cost of Justicelink at the time".

"The full range of functionality wasn't included in the original estimate and we know expect the end result will be a much better product overall," he told ZDNet Australia.

While the service has not been fully integrated to date, several of its functions are already operational in the Supreme Court, such as e-services for corporations and possessions lists, and a costs assessment application.

Implementation of all applications for District and Local courts is expected by February 2008 and July 2008 respectively, along with the remaining functions for the Supreme Court.

The Department advised that the reforms introduced through the system so far have resulted in a number of organisational improvements, and cited the streamlining of the court forms process as a significant advance, with the number of forms reduced from approximately 700 to 100.

According to the report, figures for the year ending 30 July 2007 indicated that courts across almost every jurisdiction in the state had a case clearance rate of above 100 percent, meaning not only had they been able to clear their existing cases for the year but had also been able to clear some or all of their backlogs.

The backlog is considered to be an accurate measure of court timeliness, and is defined as the percentage of pending cases within a jurisdiction that are older than the court's case disposal time.

The NSW Auditor-General's office had not responded to requests for comment at the time of publication.

Advertisement

Talkback 0 comments


Latest Videos

ZDNet's CIO Vision Series

Department of Defence | Greg Farr, CIO (part two)

In the second part of his interview, Defence CIO Greg Farr talks about outsourcing, the skills crisis and reveals his most urgent IT priority.

Sponsored content

Power Centre - Content from our premier sponsors

Blogs

  • Angus Kidman I'm a celebrity, don't back me up
    Celebrity comes with its perks — free alcohol, better-looking partners, lots of holiday time — and disadvantages — constant media intrusions, being forced to appear in films with Eddie Murphy for the long-term good of your career, and having to do mindless radio interviews with angry men who've been awake since 4am.
  • Array Lies, damned lies and telco stupidity
    Earlier this month, Telstra put out a press release trumpeting that it's come up with a new phone coaching service to help people who are "bamboozled" by their mobiles. Another excellent example of wrongheaded thinking from the mobile industry.
  • Array Dear carriers: More walking, less talking
    Sometimes, a well-placed and well-timed letter can make all the difference. Other times, it can make no difference at all — and even hurt your case. This week's missive by the Competitive Carriers' Coalition, I would suggest, falls into the latter category.
  • More blogs »

Tags

Back to top

Featured