WebCentral loses data centre in flash drought

update Users of a WebCentral Brisbane data centre today lost their access as the centre was temporarily shut down in case it overheated after its water supply was cut off.

The lack of water -- caused by the malfunction of an in-building water pump and its backup at around 11am -- meant WebCentral was unable to keep its data centre's air conditioning systems operational.

"The air-conditioning has now reached a critical point and we have been forced to shut down all data centre facilities at Wickham Street in a controlled way to minimise damage to servers and other equipment," said a statement placed on the company's Web site.

"Water supply has been re-established, but it will take some time for the cooling towers to replenish and air-conditioning to return to normal."

The statement noted WebCentral had initially shut off all non-essential services in an attempt to reduce the impact of the water supply issue.

David Lammey, the company's general manager of consumer and business, said that WebCentral first became aware of the problem around 11:15am, and confirmed the extent of the outage.

"It was the entire data centre at Wickham St that went down, ranging from our shared up to our corporate customers," said Lammey.

Lammey couldn't confirm how many customers had been affected, but said it was probably under a thousand.

"I know that across the business, in business and consumer, I've got over 60,000 accounts," he said.

"The great majority of those are over in our other datacentres. Exposure wasn't minimalised but it certainly wasn't a majority scenario."

He added most customers' services had been restored around 3pm, and said WebCentral would be working with customers individually to determine how the outage would affect their contracts financially.

Because the building hosts several other data centres operated by other companies, Lammey said WebCentral wasn't the only company affected.

He declined to say who else had suffered outages, but said at least one telecommunications company was involved.

He said WebCentral didn't know why the water pumps had failed, but would investigate the issue in conjunction with building management.

Like this article? Click below to send it to your mobile for free!

Advertisement

Talkback 4 comments

  1. Now that depends on your definition of clients. Anonymous -- 05/12/05

    I wonder.. I have 200 client sites hosted at the WC Brisbane DC.. I pay a single account, then on bill.. Is WC counting me as One client? Or 200 Clients?

    1. More than one Brisbane datacentre Anonymous -- 05/12/05

      "the WC Brisbane DC"

      WebCentral has at least two datacentres in Brisbane.

    2. Brisbane Datacentres Renai LeMay -- 05/12/05

      I have updated the story to reflect this fact.

      Kind regards,

      Renai LeMay

      (the author)

    3. I stand corrected... Anonymous -- 05/12/05

      In any case, We did lose connectivity to our dedicated boxes for a peroid of time.

      I must say, the tech guys were pretty good about it ;)

Add your opinion


ZDNet's CIO Vision Series

Video | Optus CIO Lawrie Turner

In this exclusive video interview, Optus chief information officer Lawrie Turner speaks to ZDNet.com.au about being the IT head for Australia's number two telco.

Sponsored content

Power Centre - Content from our premier sponsors

Blogs

  • Renai LeMay BarCamp buzz: Let the hacking continue
    Attending last weekend's BarCamp in Sydney, it was hard to escape the conclusion that a certain "dot-com bust" flavour had seeped into the kool aid previously being drunk by Australia's web 2.0 and early stage start-up sector.
  • Array NBN needs workers on board
    Without consensus on labour issues, the eventual winner of the NBN may end up as little more than a lame duck and a cashed-up symbol of the conflict between the desire for progress and the lack of mechanisms to deliver it.
  • Array D'Ascenzo: Read p23 of security review
    Following yesterday's admission by the Australian Taxation Office that its courier had lost a CD containing the details of 3,000 self-managed super funds, it wants to review how it handles information. My suggestion: go back to the review completed in April.
  • More blogs »

Tags

Back to top

Featured