The building could structurally house ten of the generators, seven metres in length and three metres in height, although at present only six are being installed — four on line and two as backup.
The number of generators will provide 99.9999 per cent availability to the data centre.
Ten generators would use around 200,000 litres of fuel a year, according to Andrea.
(Credit: Paul Riley)













Why put the generators on the 5th floor rather then the ground floor?